CONSTRUCTION OF DRAIN SYSTEM WITH CAPACITY OF 300 TM3 PER DAY IN TURKMENISTAN


On October,29,2015 The drain system with capasity of 300 tm3 per day is put in commission


In present time the object is in operation under warranty. 

28/09/2016 President of Turkmenistan visited the object to inspect during the working trip arround the capital





Foto from the opening ceremony 29/10/2015

________1.jpg

________2.jpg

___.jpg

IMG_4154____.jpg


IMG_4276____.jpg


The drain system with capacity of 300 tm3 per day, which is currently under construction, is designed for cleaning the domestic runoffs, which are gathered in the drain tunnel and then transferred through dropping device to receiving chamber of the main drain pumping station. Then runoffs are transferred through pumping pipes to the cleaning station.

Complex construction of DKT and KOS-300 is a part of a program for city infrastructure development, drop-off environmental protection, environmental and sanitary improvement in the city. The proposed drain cleaning technology is modern waste-free production, because the cleaned and bacteria-free water is used for watering, and the dried sludge is used as a fertilizer.

ochist2.jpg

To clean water, a biological, multi-chamber, anaerobic and aerobic method is used. Through the grills and sand-catchers wastewaters are cleaned from big and small garbage, then the water passes three special zones in air-tank: anaerobic, anoxic and aerobic, where fermentation processes take place. In a certain time the whole water mass gets into the biggest air-tank, to where the high-pressured air (about 0.5 atm.) is supplied with a capacity of 14,000 cub. m/hr. The air is supplied through aerators on the bottom of the air-tank with 0.5 mm bubbles which provide the finishing restructuring of organic compounds into non-organic with a help of bacteria. Then the whole mass is transferred to the secondary sump, defended and decontaminated. The bottom sludge of the secondary sump is transferred to anaerobic zone in air-tank. In average, water passes this way for 7 times. It should be mentioned that the whole cleaning system is a complicated technological process with back-feeds and is controlled by the technology control system, built on the basis of modern controllers and detectors. Decontaminated water and dry sludge are the outputs of the system. If an emergency situation takes place, slump is released to reserve areas.


 

The total square of the area is 75 ha. The technological cleaning process is supported with the following buildings and constructions at the site:

  1. Main wastewater pump station.
  2. Receiving chamber.
  3. Grillage building (two).
  4. Sand catchers (8 conveyors).
  5. Air-tanks (16).
  6. Secondary sumps (16).
  7. Pumping station for the secondary sumps draining (4).
  8. Sludge pump station (two).
  9. Air station (one building).
  10. Sludge-pressers (three).
  11. Aerobic stabilizers (4).
  12. Wastewater decontaminating unit (one).
  13. Sludge areas (16).
  14. Sand bunkers building (two).
  15. Water supply unit (one).

Besides the above mentioned technological buildings, there is an administrative block, garage for 10 cars, wheels washing and cars repair unit at the site.


IMG_8782____.jpg

IMG_0078____.jpg

IMG_1003____.jpg

IMG_1018____.jpg

IMG_1019____.jpg

IMG_1038____.jpg

IMG_0103____.jpg

IMG_0013____.jpg

IMG_0132____.jpg

IMG_4030____.jpg

IMG_0088____.jpg

IMG_9773____.jpg


Download presentation

icon_pdf.jpg
Construction of drain system.pdf  (2.68 MB)





Current Progects


Construction Aassociation Interbudmontazh
All rights reservedfacebook.png

Developed by Deep Vision

01013, Ukraine, Kyiv, Promyslova str, 1
Tel.: (380 44) 495-27-90
Fax: (380 44) 495-27-92
E-mail: